Public Works CIP Projects
The Public Works Department has two major priorities as identified in the 2011-12 FY Capital Improvement Program. Those priorities include:
- Maintenance of existing streets and facilities
- Improvements to Woods Chapel Road
Below is a list of capital projects related to these two major priorities, including estimated start dates, completion dates, cost and a staff contact for each project.
2012 Street Overlay Program
- Start Date: Spring 2012
- Completion: Summer 2012
- Cost: $2,300,000
- Contact: Pat Capranica, (816) 228-0121
List of streets will be determined once the contract has been awarded
2012 CDBG Sidewalk Program
- Start Date: Summer 2012
- Completion: Fall 2012
- Cost: $150,000.00
- Contact: Jeff Sell, (816) 228-0121
Sni-A-Bar Wastewater Treatment Plant Expansion
- Start Date: Spring 2010
- Completion: Summer 2012
- Cost: $25,000,000
- Contact: Chris Sandie, (816) 228-0195
Woods Chapel Road Project
- Completion Date: Spring 2014
- Contact: Jeff Sell, (816-228-0121)
|