Public Works CIP Projects
The Public Works Department has two major priorities as identified in the 2011-12 FY Capital Improvement Program. Those priorities include:

  • Maintenance of existing streets and facilities
  • Improvements to Woods Chapel Road

Below is a list of capital projects related to these two major priorities, including estimated start dates, completion dates, cost and a staff contact for each project.

2012 Street Overlay Program
  • Start Date: Spring 2012
  • Completion: Summer 2012
  • Cost: $2,300,000
  • Contact: Pat Capranica, (816) 228-0121

List of streets will be determined once the contract has been awarded

2012 CDBG Sidewalk Program
  • Start Date: Summer 2012
  • Completion: Fall 2012
  • Cost: $150,000.00
  • Contact: Jeff Sell, (816) 228-0121

Sni-A-Bar Wastewater Treatment Plant Expansion
  • Start Date: Spring 2010
  • Completion: Summer 2012 
  • Cost: $25,000,000
  • Contact: Chris Sandie, (816) 228-0195

Woods Chapel Road Project
  • Start Date: Summer 2012
  • Completion Date: Spring 2014
  • Cost: $15,000.00
  • Contact: Jeff Sell, (816-228-0121)